Initial verification, periodic inspection and testing don't happen in a vacuum. Every job you sign off sits inside a legal and regulatory framework, and 2391 candidates are regularly caught out mixing up what's statutory (law, must comply) versus non-statutory (guidance, best practice, but still expected in industry).
Statutory = Act or Regulation, passed by Parliament, enforceable by law. Non-statutory = Standard, Code of Practice or Guidance Note, written by a body like the IET or BSI, used as the accepted method of meeting the law.
Initial verification is the full check carried out before a new installation (or an alteration/addition) is energised and put into service. It is required by BS 7671 Part 6, and it must be planned before work starts, not bolted on at the end.
It has a strict order: inspection first, then testing, then results are recorded on the appropriate certificate.
Tests must be done in this order because each one relies on the previous one being safe/valid:
1. Continuity of protective conductors (including main and supplementary bonding).
2. Continuity of ring final circuit conductors (line, neutral, cpc).
3. Insulation resistance.
4. Protection by SELV, PELV or electrical separation (where used).
5. Insulation of non-conducting floors and walls (if relied on for protection, rare).
6. Polarity.
7. Earth electrode resistance (where applicable, e.g. TT systems).
8. Prospective fault current (PFC/PSCC).
9. Earth fault loop impedance (Zs).
10. Additional protection - RCD operation (function test button, then disconnection/trip times with a test instrument).
11. Functional testing - switchgear, controls, interlocks, RCDs operate correctly; check phase sequence on three-phase.
The first four/five are dead tests, done with supply disconnected. Once dead tests pass safely, the supply can be energised for polarity confirmation and then the live tests (Zs, PFC, RCD, functional).
Electrical installations degrade over time - insulation ages, connections loosen, environments change. BS 7671 (via Regulation 651.1 and the IET Guidance Note 3) requires periodic inspection and testing to confirm an installation remains safe for continued use. The output document is the Electrical Installation Condition Report (EICR), never called a 'certificate' - it reports on an EXISTING installation, it does not certify new work.
Initial verification (EIC) happens on new work before it's energised and follows Part 6 in full, including dead tests like continuity and insulation resistance on every circuit.
Periodic inspection (EICR) is mostly a visual, in-service inspection, with dead and live testing applied selectively - full dead testing is not repeated on every circuit if the installation is safe to test that way.
These are guidance figures from GN3, not fixed law - risk assessment can shorten or lengthen them.
Three observation codes are used on the EICR schedule of items:
A C1 or C2 (or an FI) makes the overall assessment UNSATISFACTORY. C3 alone still gives SATISFACTORY.
Continuity and insulation resistance (IR) testing are dead tests, done before energising a circuit. They confirm conductors are sound and intact, and that insulation between conductors, and between conductors and earth, is good enough to prevent fault current, shock or fire. Both are covered under BS 7671 Part 6 and the GN3 sequence, always carried out in this order: continuity first, then IR, before you ever apply power.
Always: continuity (R1+R2, ring tests) then insulation resistance, then polarity, THEN energise for earth fault loop impedance and RCD testing. Never skip straight to IR without proving continuity first, as a broken conductor can give a falsely reassuring high IR reading.
These are dead-testing-then-live-testing steps that confirm a circuit is safe to energise and will disconnect fast enough under fault conditions. They sit near the end of the initial verification sequence, after continuity and insulation resistance, and are required by BS 7671 Part 6.
Dead tests first (continuity, insulation resistance, polarity by continuity) then energise safely and carry out live polarity check, Zs, and RCD tests, recording all results on the schedule of test results.
Every inspection and test must end in paperwork that proves the installation is safe to energise or continue in use. BS 7671 sets out three main certificate types plus supporting schedules, and getting the right one for the right job is a common exam trap.
Any C1 or C2 makes the overall EICR assessment unsatisfactory.
The person who designs, constructs, inspects and tests each signs the relevant declaration on an EIC, confirming they take responsibility for that part of the work. On an EICR only one person, the inspector, signs, but they must be competent to do so.
The person ordering the work should keep certificates for the life of the installation, and copies should be given to the client on completion, ideally within a reasonable time frame such as as soon as practicable.