← PRINCE2 Foundation Practice
Test yourself →

PRINCE2 principles

What are the PRINCE2 principles?

PRINCE2 is built on 7 principles. They are universal, self-validating and empowering. All 7 MUST be applied to every project - if even one is missing, it is not a PRINCE2 project. Unlike themes and processes, principles are never tailored away.

The 7 principles

  • Continued business justification - there must be a justifiable reason to start the project, it must remain valid throughout, and it is recorded in the Business Case.
  • Learn from experience - lessons are sought, recorded and acted on at the start, throughout and at the end of a project. Never assume there is nothing to learn.
  • Defined roles and responsibilities - the project has an organisation structure that engages the business, user and supplier interests, with clear accountability for everyone involved.
  • Manage by stages - the project is planned, monitored and controlled on a stage-by-stage basis, giving senior management control points at the end of each management stage.
  • Manage by exception - each management level is given tolerances (time, cost, quality, scope, benefits, risk) against which it can operate without needing to escalate; exceeding tolerance triggers an escalation to the next level up.
  • Focus on products - the project focuses on the definition and delivery of products, particularly their quality requirements, not just on the activities needed to produce them.
  • Tailor to suit the project - PRINCE2 is tailored to suit the project's environment, size, complexity, importance, capability and risk. Tailoring is not the same as embellishing or adding to the method.

Common mistakes to avoid

  • Do not confuse principles with themes (there are 7 of each, but themes CAN be tailored, principles cannot).
  • Do not think 'manage by exception' means no reporting - exception reports are still raised when tolerance is forecast to be exceeded.
  • Do not think tailoring means skipping principles or roles - it means adapting HOW they are applied, not whether.
  • Remember all 6 tolerance areas for manage by exception: time, cost, quality, scope, benefits and risk - not just time and cost.
  • Learn from experience applies at ALL points (start, during, end) - not just as a lessons report at closure.

Exam tip

Questions often give a scenario and ask which principle is being illustrated or breached. Memorise the 7 names precisely (word order matters, e.g. 'continued business justification' not 'business justification continues') and match the scenario keyword to the principle.

  • There are exactly 7 PRINCE2 principles and all 7 must be applied on every genuine PRINCE2 project.
  • The 7 principles are: continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, tailor to suit the project.
  • Principles are universal (apply to every project), self-validating (proven in practice) and empowering (give practitioners confidence and structure).
  • Unlike the 7 themes, the 7 principles can never be tailored out or ignored - only HOW they are applied is tailored.
  • Continued business justification means the Business Case is checked and remains valid at every key decision point, not just at project start.
  • Manage by exception uses 6 tolerance areas: time, cost, quality, scope, benefits and risk.
  • An exception occurs when a forecast shows a tolerance will be exceeded, triggering escalation to the next management level via an exception report.
  • Manage by stages means senior management (the Project Board) authorises the project one management stage at a time, not all at once.
  • Focus on products means quality criteria and product descriptions drive the work, not just a list of activities or tasks.
  • Learn from experience requires lessons to be sought at project start, logged throughout in the Lessons Log, and reported at the end via a Lessons Report.
  • Defined roles and responsibilities requires representation of business, user and supplier interests on the project management team.
  • Tailoring adjusts PRINCE2 to the project's size, complexity, risk, capability and environment - it must never remove mandatory elements like the principles.
How many PRINCE2 principles are there, and can any be skipped?
7 - all must be applied to every PRINCE2 project; none can be skipped or tailored away.
tap to reveal
Name all 7 PRINCE2 principles.
Continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, tailor to suit the project.
tap to reveal
What are the 3 characteristics of PRINCE2 principles?
Universal, self-validating, empowering.
tap to reveal
Which principle is directly linked to the Business Case theme?
Continued business justification.
tap to reveal
What document captures ongoing lessons throughout the project?
The Lessons Log, feeding a Lessons Report at closure - part of the learn from experience principle.
tap to reveal
What are the 6 tolerance areas used in manage by exception?
Time, cost, quality, scope, benefits, risk.
tap to reveal
What triggers an exception report?
A forecast that a tolerance level will be exceeded.
tap to reveal
Which principle means the project is broken into management stages with Project Board authorisation at each boundary?
Manage by stages.
tap to reveal
Which principle ensures business, user and supplier interests are all represented?
Defined roles and responsibilities.
tap to reveal
What does focus on products emphasise over a simple task list?
Product definitions and their quality criteria/requirements.
tap to reveal
Can themes be tailored? Can principles be tailored?
Themes can be tailored; principles cannot - they apply universally.
tap to reveal
What does the tailor to suit the project principle actually adjust?
How PRINCE2 is applied (based on size, complexity, risk, capability, environment), not whether mandatory elements are used.
tap to reveal
At what points in a project should you learn from experience?
At the start, throughout, and at the end of the project.
tap to reveal
True or false: manage by exception means senior management is only involved when something goes wrong.
True in terms of routine control - within tolerance the level below manages independently; escalation only happens when tolerance is forecast to be exceeded.
tap to reveal
Why is continued business justification checked throughout, not just at the start?
Because a project must remain worthwhile - if the Business Case becomes invalid, the project should be stopped or changed.
tap to reveal

Themes (business case, organisation, quality)

Why themes matter

The seven PRINCE2 themes are the aspects of project management that must be addressed continually. This topic covers three of them: Business Case, Organization and Quality.

Business Case theme

The Business Case answers one question: is this project desirable, viable and achievable, and does it remain so?

  • It is developed in Starting Up a Project and refined in Initiating a Project, then verified by the Project Board at every stage boundary.
  • The Executive owns the Business Case throughout the project - not the Project Manager.
  • PRINCE2 uses the output-outcome-benefit chain: a project delivers outputs, which enable outcomes, which realise benefits.
  • Two techniques support it: cost-benefit analysis and investment appraisal.
  • The Benefits Review Plan defines how and when benefits will be measured - some benefits are only measurable after the project closes, so this plan can outlive the project.
  • Common mistake: thinking the Project Manager owns the Business Case. Remember - Executive owns it, Project Manager maintains supporting documents like the Benefits Review Plan.

Organization theme

This theme defines the roles and responsibilities in the temporary PRINCE2 project management team, based on a four-level structure: Corporate/programme management, Project Board, Project Manager, Team Manager(s).

  • The Project Board has three roles: Executive (represents the business), Senior User (represents users, commits user resources, ensures benefits are realised) and Senior Supplier (represents supplier interests, ensures product quality from a supplier viewpoint).
  • The Executive is ultimately accountable - only one person can hold this role.
  • Project Assurance is independent of the Project Manager and checks the project on behalf of the Board members.
  • Change Authority is a role the Board can delegate to authorise changes within set limits.
  • Project Support provides administrative help and can include configuration management.
  • Common mistake: confusing Project Assurance (independent checking) with Project Support (admin help) - they are different roles.

Quality theme

Quality is about ensuring the project delivers products that are fit for purpose - meeting user needs, not just conforming to a specification.

  • Quality planning happens early: quality criteria and quality methods are captured in the Project Product Description and Product Descriptions.
  • Quality control is carried out through quality methods - mainly quality inspection (e.g. reviews) and quality testing.
  • The Quality Register is the log that records all planned and completed quality activities and their status.
  • Two key documents: the Quality Management Strategy (how quality will be managed) and the Quality Register (tracking log).
  • Distinguish quality assurance (independent check that the approach is being followed correctly, done outside the project) from quality control (checking specific products against criteria, done within the project).
  • Common mistake: mixing up the Quality Management Strategy (the plan) with the Quality Register (the record).
  • The Executive - not the Project Manager - owns the Business Case throughout the project.
  • The output-outcome-benefit chain: outputs enable outcomes, outcomes realise benefits.
  • The Benefits Review Plan can extend beyond project closure because some benefits only show up later.
  • The Project Board has exactly three roles: Executive, Senior User, Senior Supplier.
  • Only one person can hold the Executive role - it cannot be shared.
  • Project Assurance is independent of the Project Manager and reports to the Project Board.
  • Change Authority is a role the Project Board may delegate to approve changes within agreed limits.
  • The Project Product Description captures the project-level quality criteria and acceptance criteria.
  • The Quality Register logs all planned and completed quality activities and their status.
  • Quality assurance is independent and external to the project team; quality control happens within the project.
  • The Quality Management Strategy defines how quality will be managed on the project.
  • Senior User commits user resources and is accountable that products meet user needs and benefits are realised.

Themes (risk, change, progress, plans)

Why themes exist

Themes are the 7 aspects of project management that must be applied continually throughout a PRINCE2 project. This topic covers four of them: Risk, Change, Progress, and Plans. Each theme has a specific purpose and must be tailored, not skipped.

Risk theme

The purpose of the Risk theme is to identify, assess and control uncertainty. PRINCE2 uses a Risk Management Procedure with 5 steps: Identify, Assess, Plan, Implement, Communicate (this last one runs throughout, not as a single step). Risks are recorded in the Risk Register. Each risk has a probability, impact and proximity. Responses to threats are: Avoid, Reduce, Fallback, Transfer, Accept, Share. Responses to opportunities are: Exploit, Enhance, Reject, Share. A common mistake is confusing risk responses for threats with those for opportunities - remember Share applies to both.

Change theme

The purpose of the Change theme is to identify, assess and control any potential and approved changes to baselines. Three types of issue: Request for Change, Off-Specification, and Problem/Concern. All issues are logged in the Issue Register and assessed for severity. Changes go through Issue and Change Control Procedure. Configuration Management supports this by tracking product versions - the 5 core activities are Planning, Identification, Control, Status Accounting, Verification and Audit. Do not confuse an Off-Specification (product fails to meet spec) with a Request for Change (a wanted change to an agreed baseline).

Progress theme

The purpose of the Progress theme is to establish mechanisms to monitor and compare actual achievements against planned ones, and to control any unacceptable deviations. Progress is controlled using tolerances across 6 targets: Time, Cost, Quality, Scope, Risk, Benefits (remember: TeCQuSRB, often shortened to Time/Cost/Scope/Quality plus Risk/Benefit). If tolerance is forecast to be exceeded, an exception is raised via an Exception Report to the next level up. Management stages and management by exception are the key mechanisms - they let the Project Board delegate day-to-day authority while retaining control.

Plans theme

The purpose of the Plans theme is to facilitate communication and control by defining the means of delivering products. PRINCE2 uses three levels of plan: Project Plan, Stage Plan, Team Plan (Team Plans are optional). Plans are created using Product-Based Planning, which has 4 steps: write the Project Product Description, create a Product Breakdown Structure, write Product Descriptions, create a Product Flow Diagram. A common mistake is starting planning with activities and tasks rather than products - PRINCE2 is product-focused, not activity-focused.

Exam tip

Expect questions that test the exact terminology (e.g. Fallback vs Reduce) and the correct sequence of steps in the Risk Management Procedure and Product-Based Planning.

  • The Risk Management Procedure has 5 steps: Identify, Assess, Plan, Implement, Communicate.
  • Threat risk responses are Avoid, Reduce, Fallback, Transfer, Accept, Share.
  • Opportunity risk responses are Exploit, Enhance, Reject, Share - Share is common to both.
  • There are 3 types of issue: Request for Change, Off-Specification, Problem/Concern.
  • Configuration Management has 5 core activities: Planning, Identification, Control, Status Accounting, Verification and Audit.
  • Progress is controlled using tolerance across 6 targets: Time, Cost, Quality, Scope, Risk, Benefits.
  • An Exception Report is raised when a stage or project is forecast to exceed its tolerances.
  • There are 3 levels of plan: Project Plan, Stage Plan, and (optional) Team Plan.
  • Product-Based Planning has 4 steps: Project Product Description, Product Breakdown Structure, Product Descriptions, Product Flow Diagram.
  • PRINCE2 planning is product-based, not activity-based - products are defined before activities are sequenced.
  • Risks are recorded in the Risk Register; issues are recorded in the Issue Register.
  • Management by exception allows the Project Board to delegate authority to the Project Manager within set tolerances.
What is the purpose of the Risk theme?
To identify, assess and control uncertainty throughout the project.
tap to reveal
Name the 5 steps of the Risk Management Procedure.
Identify, Assess, Plan, Implement, Communicate.
tap to reveal
List the 6 threat risk responses.
Avoid, Reduce, Fallback, Transfer, Accept, Share.
tap to reveal
List the 4 opportunity risk responses.
Exploit, Enhance, Reject, Share.
tap to reveal
What is the purpose of the Change theme?
To identify, assess and control any potential and approved changes to project baselines.
tap to reveal
What are the 3 types of issue in PRINCE2?
Request for Change, Off-Specification, Problem/Concern.
tap to reveal
What is an Off-Specification?
An issue where a product does not, or will not, meet its agreed specification.
tap to reveal
Name the 5 core activities of Configuration Management.
Planning, Identification, Control, Status Accounting, Verification and Audit.
tap to reveal
What is the purpose of the Progress theme?
To establish mechanisms to monitor and compare actual achievement against plan, and control unacceptable deviations.
tap to reveal
Name the 6 tolerance targets in the Progress theme.
Time, Cost, Quality, Scope, Risk, Benefits.
tap to reveal
When is an Exception Report raised?
When a stage or project is forecast to exceed its agreed tolerances.
tap to reveal
What is the purpose of the Plans theme?
To facilitate communication and control by defining the means of delivering the products (the where and how).
tap to reveal
Name the 3 levels of plan in PRINCE2.
Project Plan, Stage Plan, and Team Plan (Team Plan is optional).
tap to reveal
List the 4 steps of Product-Based Planning.
Write the Project Product Description, create a Product Breakdown Structure, write Product Descriptions, create a Product Flow Diagram.
tap to reveal
Is PRINCE2 planning product-based or activity-based?
Product-based - products are identified first, then activities are planned to create them.
tap to reveal

Processes overview

What the PRINCE2 processes are for

PRINCE2 has seven processes that describe WHO does WHAT and WHEN across the life of a project, from the spark of an idea through to closure. Each process is a set of activities linked to roles, and each hands off to the next. Think of the processes as the project's timeline, running alongside the seven themes (the knowledge areas applied throughout) and the seven principles (the guiding philosophy).

The seven processes in order

  • Starting up a Project (SU) - a short pre-project process to check the idea is worth doing before committing real money.
  • Directing a Project (DP) - runs from start to finish, used only by the Project Board to make key decisions.
  • Initiating a Project (IP) - builds the Project Initiation Documentation (PID), the baseline for the whole project.
  • Controlling a Stage (CS) - the day-to-day work of the Project Manager, managing each management stage.
  • Managing Product Delivery (MP) - where Team Managers accept, execute and deliver work packages.
  • Managing a Stage Boundary (SB) - reports on the current stage and plans the next one.
  • Closing a Project (CP) - a controlled, deliberate close, not an abrupt stop.

Key sequencing rules to remember

  • SU happens before the project formally exists - it produces the outline Project Brief and the Project Product Description.
  • DP is triggered by, and only responds to, the other processes - the Project Board never manages the project directly, only makes decisions at key points.
  • IP produces the PID, which the Project Board must approve before work starts.
  • CS and MP run in parallel throughout each stage - CS is the Project Manager directing, MP is the Team Manager delivering.
  • SB happens near the end of every stage except the final one, where CP takes over instead.
  • CP is a process, not just an event - it confirms acceptance, evaluates the project, and recommends follow-on actions.

Common mistakes to avoid

  • Do not confuse SU (deciding whether to start) with IP (planning how to run the whole project) - SU is quick and light, IP is thorough.
  • Do not think the Project Board manages daily work - that is DP's whole point, it is exception-driven, not hands-on.
  • Do not forget MP exists even on projects with no separate Team Manager - the Project Manager can perform the MP activities themselves.
  • Remember there is no SB at the end of the final stage - CP replaces it.
  • The seven processes are mandatory to consider, but PRINCE2 is meant to be tailored to the size and complexity of the project.
  • There are exactly seven PRINCE2 processes, running alongside seven themes and seven principles.
  • The seven processes in order are: Starting up a Project, Directing a Project, Initiating a Project, Controlling a Stage, Managing Product Delivery, Managing a Stage Boundary, and Closing a Project.
  • Starting up a Project (SU) is a short pre-project process that produces the outline Project Brief and Project Product Description.
  • Directing a Project (DP) runs from project start to finish and is used exclusively by the Project Board.
  • DP is exception-driven - the Project Board only steps in at key decision points, not day-to-day.
  • Initiating a Project (IP) produces the Project Initiation Documentation (PID), which must be approved before delivery work begins.
  • Controlling a Stage (CS) is the Project Manager's process for managing the day-to-day work within a stage.
  • Managing Product Delivery (MP) is where Team Managers accept, execute and deliver work packages.
  • Managing a Stage Boundary (SB) reports on the current stage and plans the next, and occurs at the end of every stage except the last.
  • Closing a Project (CP) replaces SB at the end of the final stage and confirms product acceptance.
  • Closing a Project is a controlled activity, not simply the project stopping or running out of time.
  • CS and MP operate in parallel throughout each management stage.
How many processes does PRINCE2 have?
Seven.
tap to reveal
List the seven PRINCE2 processes in order.
Starting up a Project, Directing a Project, Initiating a Project, Controlling a Stage, Managing Product Delivery, Managing a Stage Boundary, Closing a Project.
tap to reveal
What is the purpose of Starting up a Project (SU)?
A short pre-project process to check the project idea is viable and worthwhile before committing to it.
tap to reveal
Which two documents does SU produce?
The outline Project Brief and the Project Product Description.
tap to reveal
Who uses the Directing a Project (DP) process?
The Project Board only.
tap to reveal
How does the Project Board manage the project under DP?
By exception - it only gets involved at key decision points, not on a day-to-day basis.
tap to reveal
What key document does Initiating a Project (IP) produce?
The Project Initiation Documentation (PID).
tap to reveal
What must happen before delivery work can start in the project?
The Project Board must approve the PID.
tap to reveal
Who runs Controlling a Stage (CS)?
The Project Manager, managing the day-to-day work within a management stage.
tap to reveal
Who runs Managing Product Delivery (MP)?
Team Managers, who accept, execute and deliver work packages.
tap to reveal
Can the Project Manager perform MP activities if there is no Team Manager?
Yes - the Project Manager can carry out the MP activities themselves.
tap to reveal
What does Managing a Stage Boundary (SB) do?
Reports on the current stage's performance and plans the next stage.
tap to reveal
When does SB NOT happen?
At the end of the final stage - Closing a Project (CP) takes over instead.
tap to reveal
Is Closing a Project (CP) an abrupt stop or a controlled process?
A controlled, deliberate process that confirms acceptance and evaluates the project.
tap to reveal
Which two processes run in parallel during each stage?
Controlling a Stage (CS) and Managing Product Delivery (MP).
tap to reveal

Roles & responsibilities

Why roles matter in PRINCE2

PRINCE2 is role-based, not person-based. One person can hold several roles, and a role can be shared by several people (as long as no conflict of interest). The Project Manager cannot also be the Executive, and Project Assurance must stay independent of the Project Manager.

Project Board

The Project Board owns the project and is accountable to corporate/programme management. It has three roles:

  • Executive: chairs the board, owns the Business Case, ultimately accountable for the project's success. Only ONE Executive.
  • Senior User(s): represent(s) everyone who will use the products, specify benefits, commit user resources, and are accountable for the benefits being realised.
  • Senior Supplier(s): represent(s) those designing, developing, procuring and implementing the products; accountable for the quality of supplier deliverables.

Project Manager

Runs the project day-to-day on behalf of the Project Board: planning, delegating, monitoring and controlling. Manages Team Managers and reports progress via Highlight Reports and end-stage/exception reports.

Team Manager

Optional role (used on larger projects) that creates Work Packages into products and manages a team; reports to the Project Manager via Checkpoint Reports.

Project Assurance

Independent check, on behalf of the Project Board, that the project remains viable and is being run correctly (business, user and supplier assurance). Must NOT be delegated to the Project Manager, because it would mean checking your own work.

Change Authority

A person or group, delegated by the Project Board, given authority to approve or reject requests for change and off-specifications, often within a set change budget.

Project Support

Optional administrative role — filing, configuration management, planning tools — can be a separate person/office or covered by the Project Manager if there is no dedicated support.

Corporate/programme management

Sits above the Project Board, appoints the Executive, sets project tolerances, and receives the End Project Report.

Common exam mistakes

  • Confusing Project Assurance (independent check) with Project Support (admin help).
  • Thinking the Project Manager appoints the Executive — it is the other way round, corporate management appoints the Executive.
  • Forgetting there must be exactly one Executive but user/supplier roles can be shared or split.
  • Mixing up Highlight Reports (Project Manager to Board) with Checkpoint Reports (Team Manager to Project Manager).
  • There is only ONE Executive on the Project Board — never more than one.
  • The Project Board has three roles: Executive, Senior User, Senior Supplier.
  • The Project Manager and Project Assurance can never be the same person.
  • Senior User is accountable for specifying benefits and confirming they are realised.
  • Senior Supplier is accountable for the quality of products delivered by the supplier(s).
  • Team Manager reports progress to the Project Manager using Checkpoint Reports.
  • Project Manager reports progress to the Project Board using Highlight Reports.
  • Corporate or programme management appoints the Executive, not the Project Board itself.
  • Project Assurance covers three areas: business assurance, user assurance, supplier assurance.
  • The Change Authority is delegated approval power for changes, often with an assigned change budget.
  • Project Support and Team Manager are both optional roles — used only when the project needs them.
  • Roles can be shared by many people or one person can hold several roles, but never a conflict of interest.
How many people can be the Executive at one time?
Only one — there is always exactly one Executive.
tap to reveal
Name the three roles on the Project Board.
Executive, Senior User, Senior Supplier.
tap to reveal
Can the Project Manager also carry out Project Assurance?
No — Project Assurance must be independent of the Project Manager.
tap to reveal
Who is accountable for specifying and realising the project's benefits?
The Senior User(s).
tap to reveal
Who is accountable for the quality of the products the suppliers deliver?
The Senior Supplier(s).
tap to reveal
What report does a Team Manager send to the Project Manager?
A Checkpoint Report.
tap to reveal
What report does the Project Manager send to the Project Board?
A Highlight Report.
tap to reveal
Who appoints the Executive?
Corporate or programme management, above the Project Board.
tap to reveal
What are the three types of Project Assurance?
Business assurance, user assurance and supplier assurance.
tap to reveal
What is a Change Authority?
A person or group delegated by the Project Board to approve or reject changes, sometimes with a change budget.
tap to reveal
Is the Team Manager role mandatory?
No — it is optional and typically used on larger or more complex projects.
tap to reveal
Is Project Support mandatory?
No — it is optional; its tasks can be absorbed by the Project Manager if not set up separately.
tap to reveal
Can one person hold more than one PRINCE2 role?
Yes, provided there is no conflict of interest (e.g. Project Manager cannot also be Project Assurance).
tap to reveal
Who does the Project Board answer to?
Corporate or programme management.
tap to reveal
What document does corporate/programme management receive at project closure?
The End Project Report.
tap to reveal

Management products & tailoring

What are management products?

PRINCE2 defines three types of management product. These are NOT the specialist products the project delivers (like a bridge or an app) - they are the paperwork that runs the project.

  • Baselines - approved products that define aspects of the project and are subject to change control, eg the Project Plan, PID, Product Descriptions.
  • Records - dynamic products that maintain a log of project progress, eg the Risk Register, Issue Register, Quality Register, Daily Log, Lessons Log.
  • Reports - give a snapshot of the status of aspects of the project, eg Highlight Report, End Stage Report, End Project Report, Lessons Report.

The three levels of plan

PRINCE2 uses three levels of plan, matched to the three levels of management:

  • Project Plan - Board level, whole project, mandatory.
  • Stage Plan - Team Manager/PM level, one management stage at a time, mandatory.
  • Team Plan - Team Manager level, optional, used when work is delegated.

An Exception Plan replaces a Stage or Project Plan when a tolerance has been (or is forecast to be) exceeded - it covers the period from now to the end of the current stage.

Key management products to know cold

  • Business Case - the justification, owned by the Executive, checked at every stage boundary.
  • Project Initiation Documentation (PID) - the baseline for the whole project, created during Initiating a Project.
  • Product Description - defines a product's purpose, composition, derivation, format, and quality criteria/tolerance/method.
  • Work Package - the agreement between PM and Team Manager to deliver one or more products.
  • Communication Management Approach - defines how and when communication will happen.

Tailoring

Tailoring means adapting PRINCE2 to suit the project's context - size, complexity, importance, capability and risk. Tailoring is NOT the same as embedding (which is adopting PRINCE2 organisation-wide as standard practice).

  • The seven PRINCE2 principles are never tailored - they always apply.
  • Themes, processes and management products CAN and SHOULD be tailored.
  • You can combine management products (eg merge the Risk and Issue Register) but you must never lose the required information.
  • Justify and record every tailoring decision, normally in the PID.

Common mistakes

  • Confusing baselines with records - baselines change only through change control, records are updated routinely as work happens.
  • Thinking tailoring means dropping themes or processes - you tailor how they're applied, not whether they're applied.
  • Believing small projects skip the PID - it can be brief, but it must still exist.
  • Mixing up Product Description (defines what a product should be) with Product Status Account (reports on what state products are actually in).
  • There are three types of management product: baselines, records and reports.
  • Baselines are subject to formal change control; records and reports are not.
  • There are three levels of plan: Project Plan, Stage Plan and Team Plan.
  • The Team Plan is the only one of the three plan levels that is optional.
  • An Exception Plan replaces a Stage or Project Plan once tolerance is or will be exceeded, covering the time to the end of the current stage.
  • A Product Description covers purpose, composition, derivation, format and quality criteria, tolerance and method - not just a name.
  • The PID (Project Initiation Documentation) is the baseline against which the whole project is measured, created in Initiating a Project.
  • The Business Case is a baseline management product owned by the Executive and reviewed at every stage boundary.
  • Tailoring adapts PRINCE2 to the project's context - size, complexity, importance, capability and risk.
  • The seven principles are never tailored; themes, processes and management products can be.
  • Embedding is organisation-wide adoption of PRINCE2 as standard; tailoring is adapting it for one specific project.
  • Tailoring decisions must be justified and recorded, usually in the PID.
What are the three types of management product in PRINCE2?
Baselines, records and reports.
tap to reveal
What distinguishes a baseline from a record?
A baseline is subject to formal change control once approved; a record is simply updated as work progresses.
tap to reveal
Name three example baseline products.
Project Plan, PID, and Product Description.
tap to reveal
Name three example record products.
Risk Register, Issue Register and Quality Register (or Daily Log/Lessons Log).
tap to reveal
Name three example report products.
Highlight Report, End Stage Report and End Project Report.
tap to reveal
What are the three levels of plan in PRINCE2?
Project Plan, Stage Plan and Team Plan.
tap to reveal
Which level of plan is optional?
The Team Plan.
tap to reveal
When is an Exception Plan produced?
When a tolerance has been or is forecast to be exceeded; it replaces the Stage or Project Plan and covers the time to the end of the current stage.
tap to reveal
What does a Product Description define?
A product's purpose, composition, derivation, format, and its quality criteria, tolerance and quality method.
tap to reveal
Who owns the Business Case?
The Executive.
tap to reveal
What is tailoring?
Adapting PRINCE2's themes, processes and management products to suit the project's size, complexity, importance, capability and risk.
tap to reveal
Can the seven principles be tailored?
No - the principles are never tailored, they always apply.
tap to reveal
What is the difference between tailoring and embedding?
Tailoring adapts the method for a specific project; embedding is adopting PRINCE2 as standard practice across an organisation.
tap to reveal
Where should tailoring decisions be recorded?
In the PID, with justification for each decision.
tap to reveal
What is the difference between a Product Description and a Product Status Account?
A Product Description defines what a product should be; a Product Status Account reports on the actual current state of specified products.
tap to reveal