The DSDM Agile Project Framework

## Introduction to The DSDM Agile Project Framework

DSDM (Dynamic Systems Development Method) is a comprehensive agile project delivery framework that provides a robust approach to managing, planning, and controlling agile projects. It focuses on delivering business value quickly and effectively, ensuring projects are delivered on time and on budget, and that the solution is fit for purpose. DSDM is a framework, not just a methodology, meaning it provides a structure that can be adapted to various project contexts.

## DSDM Philosophy and Principles

The DSDM Philosophy states: "The best way to deliver value is to deliver frequently and incrementally, in a collaborative, self-organising team, with a focus on business needs."

This philosophy is supported by 8 Principles that guide all DSDM projects:

  • Focus on the Business Need: Every decision must align with business objectives.
  • Deliver on Time: Punctual delivery is a key measure of success.
  • Collaborate: Active user involvement and close cooperation are essential.
  • Never Compromise Quality: Quality is a prerequisite, not a variable.
  • Build Incrementally from Firm Foundations: Start with a clear understanding and evolve the solution.
  • Develop Iteratively: Embrace change and refine solutions through repeated cycles.
  • Communicate Continuously and Clearly: Effective communication is vital for success.
  • Demonstrate Control: Maintain transparency and control throughout the project.

## The DSDM Lifecycle

The DSDM framework defines a structured, yet agile, lifecycle with 6 phases:

  • Pre-Project: Ensures projects are set up correctly.
  • Feasibility: Establishes if the project is viable from a business and technical perspective.
  • Foundations: Defines the 'what' and 'how' of the solution at a high level.
  • Evolutionary Development: Iteratively develops the solution, delivering increments.
  • Deployment: Releases the tested increment into operational use.
  • Post-Project: Reviews the project's success and benefits realisation.

## Key DSDM Techniques and Roles

MoSCoW Prioritisation is a core technique used to prioritise requirements into:

  • Must Have: Non-negotiable requirements.
  • Should Have: Important, but not critical, can be deferred.
  • Could Have: Desirable, but less critical, easily dropped.
  • Won't Have: Requirements agreed not to be delivered in this increment.

Timeboxing is another fundamental technique, fixing time and cost while allowing the scope (specifically 'Could Have' and 'Should Have' requirements) to vary to meet deadlines. Other techniques include Facilitated Workshops, Modelling, and Prototyping.

Key DSDM roles include the Business Sponsor (funding, strategic direction), Project Manager (overall project management), Business Ambassador (represents business needs in the team), Technical Coordinator (technical architecture), and Solution Developer (builds the solution).

  • DSDM is an agile project delivery framework focused on delivering business value on time and on budget.
  • The DSDM Philosophy emphasizes frequent, incremental delivery in collaborative, self-organising teams.
  • There are 8 DSDM Principles that guide all projects.
  • MoSCoW is the primary prioritisation technique, categorising requirements as Must, Should, Could, or Won't Have.
  • Timeboxing fixes time and cost, allowing scope to be flexible to ensure on-time delivery.
  • The DSDM lifecycle consists of 6 phases: Pre-Project, Feasibility, Foundations, Evolutionary Development, Deployment, and Post-Project.
  • Quality is never compromised in DSDM; it is a prerequisite for delivery.
  • The Business Ambassador role ensures business needs are continuously represented within the development team.
What is the primary prioritisation technique used in DSDM?
MoSCoW (Must Have, Should Have, Could Have, Won't Have)
tap to reveal
How many DSDM Principles are there?
Eight
tap to reveal
What is the core purpose of Timeboxing in DSDM?
To fix time and cost, allowing scope to vary to ensure on-time delivery.
tap to reveal
Name the 6 phases of the DSDM project lifecycle.
Pre-Project, Feasibility, Foundations, Evolutionary Development, Deployment, Post-Project
tap to reveal
Which DSDM principle states that quality is a prerequisite and never compromised?
Never Compromise Quality
tap to reveal
Which DSDM role represents the business needs and ensures the solution is fit for purpose?
Business Ambassador
tap to reveal
What does the 'M' in MoSCoW stand for?
Must Have
tap to reveal
What is the DSDM Philosophy focused on?
Delivering value frequently and incrementally, in a collaborative, self-organising team, with a focus on business needs.
tap to reveal

Philosophy, Principles, and Project Variables

## AgilePM Philosophy: DSDM's Core

AgilePM is built upon the Dynamic Systems Development Method (DSDM), a proven agile framework. Its philosophy centers on delivering business value quickly and continuously. Unlike traditional approaches, DSDM aims for fixed time and fixed cost projects, achieving this by allowing scope to flex. This ensures early and frequent delivery of working solutions, fostering a collaborative environment where stakeholders are actively involved throughout the project lifecycle. A core tenet is the no blame culture, promoting learning and adaptation.

## The 8 Principles of AgilePM

These principles guide all AgilePM projects:

  • Focus on the Business Need: Every effort must contribute to a clear business objective.
  • Deliver on Time and to Budget: Project control is paramount; timeboxes and budgets are fixed.
  • Collaborate: Active involvement and shared ownership among all stakeholders.
  • Never Compromise Quality: Quality is defined and agreed upon early and is non-negotiable.
  • Build Incrementally from Firm Foundations: Start with a solid understanding, then evolve the solution.
  • Develop Iteratively: Embrace change and refine solutions through repeated cycles.
  • Communicate Continuously and Clearly: Open and honest communication is vital for shared understanding.
  • Demonstrate Control: Maintain visibility and manage the project proactively.

## Project Variables: Fixed Time, Fixed Cost, Variable Scope

A fundamental difference in AgilePM is its approach to project variables. Traditional projects often fix scope and allow time/cost to vary, leading to potential overruns. AgilePM, conversely, fixes time and cost, treating them as constraints. To achieve this, scope becomes the variable. This is managed through effective prioritization using techniques like MoSCoW (Must Have, Should Have, Could Have, Won't Have this time).

Quality is considered a fixed, non-negotiable element. By prioritizing requirements, the most critical features (Must Haves) are always delivered, ensuring a minimum viable product within the agreed timeframe and budget, while less critical features (Should/Could Haves) can be deferred or dropped if necessary. This approach guarantees a working solution on time and within budget, delivering maximum possible business value.

  • AgilePM is founded on the **DSDM** framework, focusing on business value.
  • The core project variables are **fixed time, fixed cost, variable scope**.
  • **Quality** is a non-negotiable, fixed constraint in AgilePM.
  • **MoSCoW** prioritization is key to managing variable scope.
  • AgilePM is guided by **8 Principles** for effective project delivery.
  • **Collaboration** and continuous communication are essential principles.
  • **Timeboxing** is a primary technique for delivering on time and to budget.
  • A "no blame" culture supports learning and adaptation in AgilePM.
What agile framework is AgilePM based on?
DSDM (Dynamic Systems Development Method).
tap to reveal
What are the three project variables in AgilePM, and which are fixed/variable?
Time (fixed), Cost (fixed), Scope (variable).
tap to reveal
What is the primary technique used to manage variable scope in AgilePM?
MoSCoW prioritization (Must Have, Should Have, Could Have, Won't Have this time).
tap to reveal
How many principles guide an AgilePM project?
Eight (8).
tap to reveal
Which AgilePM principle states that quality should never be compromised?
"Never Compromise Quality."
tap to reveal
What is a key technique for delivering on time and to budget in AgilePM?
Timeboxing.
tap to reveal
What is the first principle of AgilePM?
Focus on the Business Need.
tap to reveal
What does the AgilePM philosophy prioritize delivering early and continuously?
Business value.
tap to reveal

DSDM Roles and Responsibilities

## DSDM Roles and Responsibilities

DSDM (Dynamic Systems Development Method), upon which AgilePM is based, defines a comprehensive set of roles designed to ensure effective collaboration, clear accountability, and successful project delivery. These roles are typically categorised into three levels:

  • Business Roles: Focus on the 'what' and 'why' – ensuring the project delivers real business value.
  • Management Roles: Focus on the 'how' – managing the project process and environment.
  • Technical Roles: Focus on the 'build' – creating and testing the solution.

Key Business Roles

  • Business Sponsor: The ultimate authority for the project, accountable for its business case, ROI, and ensuring adequate funding and resources. They empower the Business Visionary.
  • Business Visionary: Defines the project's overall vision, high-level scope, and requirements. They represent the business user community at a strategic level and ensure the solution aligns with business needs.
  • Business Ambassador: Represents specific business areas or user groups. They provide detailed business requirements, actively participate in workshops and reviews, and are empowered to make decisions on behalf of their users.
  • Business Advisor: Provides specialist input (e.g., legal, security, marketing) as required, typically not a full-time role.

Key Management Roles

  • Project Manager (PM): Facilitates the project, manages the process, risks, and budget. The PM focuses on the project lifecycle and ensures effective communication and collaboration across all stakeholders.
  • Team Leader: Leads the Solution Development Team (SDT), facilitates daily stand-ups, removes impediments, and mentors team members. They ensure the team adheres to DSDM principles and practices.

Key Technical Roles

  • Technical Coordinator (TC): Ensures the technical quality, consistency, and architectural integrity of the solution. They define technical standards and mentor technical team members.
  • Solution Developer: Designs, builds, and tests parts of the solution, collaborating closely within the SDT to deliver increments.
  • Solution Tester: Tests the solution to ensure quality and adherence to requirements, working with developers and business representatives.

Supporting Roles

Supporting roles like the Workshop Facilitator, DSDM Coach, and DSDM Trainer provide specialist assistance to ensure efficient working practices and DSDM adoption. All DSDM roles emphasise empowerment, collaboration, and continuous communication to deliver value incrementally.

  • DSDM roles are structured across three levels: Business, Management, and Technical.
  • The **Business Sponsor** is ultimately accountable for the project's business case and ROI.
  • The **Business Visionary** defines the high-level scope and overall vision for the solution.
  • The **Business Ambassador** provides detailed requirements and represents specific user groups.
  • The **Project Manager** manages the project process, risks, and budget, not the detailed solution development.
  • The **Team Leader** leads the Solution Development Team and removes impediments.
  • The **Technical Coordinator** ensures the technical quality and architectural integrity of the solution.
  • All DSDM roles are empowered to make decisions within their defined scope, promoting efficiency.
Who holds ultimate accountability for the project's business case and ROI?
The **Business Sponsor**.
tap to reveal
Which role defines the overall vision and high-level requirements for the solution?
The **Business Visionary**.
tap to reveal
Which role provides detailed business requirements and represents specific user groups?
The **Business Ambassador**.
tap to reveal
What is the primary responsibility of the **Project Manager** in DSDM?
To manage the project process, risks, and budget, ensuring effective communication and collaboration.
tap to reveal
Who is responsible for leading the Solution Development Team and removing impediments?
The **Team Leader**.
tap to reveal
Which role ensures the technical quality, consistency, and architectural integrity of the solution?
The **Technical Coordinator**.
tap to reveal
Name the three levels at which DSDM roles are structured.
Business, Management, and Technical.
tap to reveal
What is a key characteristic of DSDM roles regarding decision-making?
Roles are empowered to make decisions within their defined scope.
tap to reveal

The DSDM Process

## The DSDM Process

The DSDM Process provides a robust, iterative, and incremental framework for agile project management, emphasizing the delivery of business value quickly and frequently. It's structured around a lifecycle designed to ensure controlled and successful project delivery, integrating principles like active user involvement and frequent delivery.

## DSDM Process Lifecycle Phases

The DSDM Process comprises six distinct, yet often overlapping, phases:

  • Pre-Project: This initial phase ensures that only well-conceived and viable projects are started. It focuses on identifying the project's business need, strategic fit, and securing initial funding and commitment.
  • Feasibility: Here, the project's overall viability is assessed from both business and technical perspectives. It answers whether the project is possible and desirable, establishing a high-level business case and understanding key risks.
  • Foundations: This phase establishes the 'what' and 'how' of the solution at a high level. It involves defining the scope, high-level requirements, architectural outline, and the project approach, including team structure and initial plan.
  • Evolutionary Development: This is the core iterative and incremental phase where the solution is built. It involves cycles of Explore, Refine, and Consolidate. Requirements are refined, the solution is developed, tested, and reviewed, continuously moving towards a deployable increment.
  • Deployment: In this phase, a tested and approved increment of the solution is released into the operational environment. It includes activities like user training, data migration, and formal handover to operational teams.
  • Post-Project: This final phase ensures that the business benefits defined in the business case are realized. It involves reviewing the project's success against objectives, identifying lessons learned, and ensuring ongoing support and maintenance for the delivered solution.

## Key Techniques within the Process

  • Timeboxing: A core DSDM technique where work is fixed into short, fixed-duration periods (timeboxes). Scope is variable and managed using prioritisation.
  • MoSCoW Prioritisation: Used extensively within timeboxes and across the project to prioritize requirements and tasks. It categorizes items as Must have, Should have, Could have, and Won't have (this time), ensuring focus on critical features.
  • Active User Involvement: DSDM stresses continuous and active engagement from business users throughout the project lifecycle, particularly during Evolutionary Development, to ensure the solution meets real business needs.
  • The DSDM Process is an iterative and incremental framework for agile project management.
  • It consists of six phases: Pre-Project, Feasibility, Foundations, Evolutionary Development, Deployment, and Post-Project.
  • **Evolutionary Development** is the central phase where solution increments are built through cycles of Explore, Refine, and Consolidate.
  • **Timeboxing** fixes time and resources, allowing scope to be flexible and managed through prioritisation.
  • **MoSCoW** is a prioritisation technique used to manage scope within timeboxes.
  • **Active User Involvement** is a fundamental DSDM principle, crucial for delivering the right solution.
  • The **Foundations** phase establishes the high-level 'what' and 'how' of the project.
  • The DSDM Process ensures business value is delivered frequently and incrementally.
What are the 6 phases of the DSDM Process?
Pre-Project, Feasibility, Foundations, Evolutionary Development, Deployment, Post-Project.
tap to reveal
What is the primary purpose of the **Pre-Project** phase in DSDM?
To ensure that only well-conceived and viable projects are started, aligned with strategic goals.
tap to reveal
Which DSDM phase focuses on establishing high-level requirements, architecture, and the project approach?
The **Foundations** phase.
tap to reveal
What three activities define the core of the **Evolutionary Development** phase?
Explore, Refine, and Consolidate.
tap to reveal
What does **MoSCoW** stand for, and what is its purpose in DSDM?
Must have, Should have, Could have, Won't have (this time). It's used for prioritising requirements and tasks.
tap to reveal
How does **Timeboxing** function within the DSDM Process?
It fixes the time and resources for a period of work, allowing the scope to be flexible and prioritised using MoSCoW.
tap to reveal
What is the main objective of the **Deployment** phase?
To release a tested and approved increment of the solution into the operational environment for end-users.
tap to reveal
Why is **Active User Involvement** considered crucial in the DSDM Process?
It ensures the solution continuously meets real business needs and delivers genuine business value.
tap to reveal

DSDM Products

## DSDM Products Overview

AgilePM (based on DSDM) projects create a set of defined products (deliverables) throughout their lifecycle. These products provide structure, maintain control, and ensure alignment with business objectives. They are categorised into Feasibility, Foundations, Evolutionary, Deployment, and Post-Project products.

A key DSDM concept is that products evolve over time, starting with high-level definitions and becoming more detailed as the project progresses. This iterative refinement supports continuous feedback and adaptation.

## Key Feasibility & Foundations Products

  • Terms of Reference (ToR): Defines the scope and objectives for the Feasibility phase. It ensures everyone understands what needs to be assessed.
  • Business Case: Justifies the project from a business perspective, outlining the expected benefits, costs, and risks. It's a living document, reviewed and updated throughout the project.
  • Prioritised Requirements List (PRL): A high-level list of all requirements, prioritised using MoSCoW (Must Have, Should Have, Could Have, Won't Have). This ensures focus on critical features.
  • Solution Architecture Definition (SAD): Describes the high-level technical architecture and design of the solution, ensuring it is fit for purpose, scalable, and maintainable.
  • Management Approach Definition (MAD): Outlines how the project will be managed, including roles, responsibilities, reporting structures, and project controls.
  • Development Approach Definition (DAD): Specifies the technical tools, techniques, environments, and standards to be used during development.

## Key Evolutionary & Deployment Products

  • Evolving Solution: This is the incremental, iterative development of the actual business solution. It includes prototypes, increments, and the final deliverable, continually refined based on feedback from stakeholders.
  • Deployment Plan: Details the strategy and activities required to release the Evolving Solution into the live environment, including training, data migration, and ongoing support arrangements.
  • Deployed Solution: The final, tested, and accepted business solution that has been successfully released into the operational environment, ready for use.

## Key Post-Project Product

  • Benefits Realisation Report: Created post-project closure, this report confirms whether the expected business benefits outlined in the Business Case have actually been achieved over time. It validates the project's ultimate success and value delivery.
  • DSDM products are deliverables created throughout the project lifecycle, providing structure and control.
  • Products are categorised into Feasibility, Foundations, Evolutionary, Deployment, and Post-Project.
  • The **Business Case** justifies the project from a business perspective and is a living document.
  • The **Prioritised Requirements List (PRL)** uses **MoSCoW** to prioritise requirements.
  • The **Evolving Solution** represents the incremental development of the actual business product.
  • The **Solution Architecture Definition (SAD)** describes the high-level technical design.
  • The **Deployed Solution** is the final, accepted product released into the live environment.
  • The **Benefits Realisation Report** confirms if expected business benefits were achieved post-project.
What is the primary purpose of the **Business Case** in DSDM?
To justify the project from a business perspective, outlining expected benefits, costs, and risks.
tap to reveal
Which DSDM product lists high-level requirements and uses MoSCoW for prioritisation?
The **Prioritised Requirements List (PRL)**.
tap to reveal
What does the **Evolving Solution** represent in a DSDM project?
The incremental and iterative development of the actual business solution, refined through feedback.
tap to reveal
What is the purpose of the **Terms of Reference (ToR)**?
To define the scope and objectives for the Feasibility phase.
tap to reveal
Which DSDM product defines the high-level technical architecture and design?
The **Solution Architecture Definition (SAD)**.
tap to reveal
What is the final, accepted product released into the operational environment called?
The **Deployed Solution**.
tap to reveal
What is the purpose of the **Benefits Realisation Report**?
To confirm, post-project, whether the expected business benefits have actually been achieved.
tap to reveal
Which DSDM product defines how the project will be managed, including roles and responsibilities?
The **Management Approach Definition (MAD)**.
tap to reveal

MoSCoW Prioritisation and Timeboxing

## MoSCoW Prioritisation

MoSCoW is a widely used prioritisation technique in AgilePM, crucial for managing scope within fixed time and cost projects. It categorises requirements to ensure the most important features are delivered first, aligning with the principle of delivering value early.

  • Must Have: These are non-negotiable requirements, absolutely essential for the solution to be viable and acceptable. Without a Must Have, the project cannot be considered a success. They should be kept to a minimum to allow flexibility.
  • Should Have: Important requirements that add significant value but are not critical for viability. Omitting them would be painful, but the solution would still be functional. These are often delivered after all Must Haves.
  • Could Have: Desirable requirements that are nice to have if time and resources permit. They offer additional benefits but are the first to be dropped under pressure, providing the primary buffer for timebox delivery.
  • Won't Have (this time): Requirements agreed to be excluded from the current delivery increment. This manages expectations and prevents future misunderstandings, while allowing for potential inclusion in later increments or projects.

Prioritisation is a collaborative effort involving business and technical stakeholders, and the relative importance of items can evolve as understanding grows and circumstances change.

## Timeboxing

Timeboxing is a core AgilePM technique involving a fixed period of time (a 'timebox') during which a team works to deliver an agreed set of outcomes. It has a non-negotiable fixed end date and fixed resources (the stable team).

The primary variable within an AgilePM timebox is scope, which is managed using MoSCoW prioritisation. This ensures that the most important features are delivered by the deadline, even if some lower-priority items need to be deferred.

Timeboxes drive focus, manage risk by forcing frequent delivery of working solutions, and provide regular opportunities for feedback and adaptation. They prevent projects from overrunning by making scope the adjustable element, not the deadline.

## MoSCoW and Timeboxing in Practice

These two techniques work hand-in-hand to deliver value within constraints. Within a timebox, the team commits to delivering all Must Haves. They then aim to deliver as many Should Haves as possible, followed by Could Haves if time permits. Won't Haves are explicitly excluded from the current timebox.

If a Must Have cannot be delivered, it triggers a serious re-evaluation of the project or timebox, as the viability of the solution is at stake. However, the flexibility to descope Should Haves and Could Haves is crucial for meeting the fixed deadline and delivering a viable, acceptable solution, embodying the AgilePM principle of 'fix time and cost, flex scope'.

  • MoSCoW categorises requirements into Must, Should, Could, and Won't Have (this time).
  • **Must Haves** are essential for the solution's viability and must be delivered.
  • **Timeboxing** fixes time and resources, making scope the primary variable.
  • The **fixed end date** of a timebox is non-negotiable in AgilePM.
  • MoSCoW prioritisation enables flexible scope management within a timebox.
  • **Won't Have (this time)** manages expectations by explicitly excluding requirements from the current delivery.
  • Within a timebox, the team commits to delivering all **Must Haves** first.
  • Lower priority items (**Shoulds**, **Coulds**) provide the buffer for meeting timebox deadlines.
What does 'M' stand for in MoSCoW?
Must Have
tap to reveal
What is the key characteristic of a 'Must Have' requirement?
Essential for the solution to be viable and acceptable; non-negotiable.
tap to reveal
What does 'W' stand for in MoSCoW?
Won't Have (this time)
tap to reveal
What is the primary variable in an AgilePM timebox?
Scope (features/requirements)
tap to reveal
What are the fixed elements of an AgilePM timebox?
Time (fixed end date) and Resources (stable team).
tap to reveal
How do MoSCoW and Timeboxing work together?
MoSCoW prioritises scope, allowing lower priority items (Shoulds, Coulds) to be descoped to meet the fixed deadline of a timebox.
tap to reveal
What happens if a 'Must Have' cannot be delivered within a timebox?
It triggers a serious re-evaluation of the project or timebox, as the solution's viability is compromised.
tap to reveal
What is the purpose of 'Won't Have (this time)'?
To manage expectations by explicitly stating what will not be delivered in the current increment, while keeping it open for future consideration.
tap to reveal

Planning and Control

## Planning and Control in AgilePM

AgilePM operates on a fixed time, fixed cost, variable scope model, making effective planning and control fundamental for project success. The central mechanism for achieving this is timeboxing.

## Timeboxing: The Core Mechanism

A Timebox is a fixed, short period of time (typically 2-4 weeks) within which a specific set of objectives must be met. It has a defined start and end date, and its scope is managed using MoSCoW prioritisation. This ensures that the most critical requirements (Must Have) are delivered first, followed by Should Have, Could Have, and finally Won't Have this time if scope needs to be adjusted. This flexibility in scope is key to delivering within fixed time and cost.

Each Timebox follows a structured cycle:

  • Kick-off: The team agrees on the Timebox objectives and initial tasks.
  • Daily Stand-ups: Short, daily meetings for the team to report progress, highlight impediments, and re-plan their work for the day.
  • Review: At the end of the Timebox, the team demonstrates the working solution to stakeholders and gathers feedback.
  • Close-out: Formal completion of the Timebox, including updating progress and capturing lessons learned.

## Levels of Planning

Planning in AgilePM occurs at multiple levels, providing increasing detail as the project progresses:

  • Project Level: The Project Plan provides a high-level overview, outlining the project's phases (e.g., Feasibility, Foundations, Exploration, Deployment) and overall timeline.
  • Phase Level: The Foundations Phase establishes the project's baseline, defining the detailed scope, solutions, and delivery approach. The Exploration Phase involves iterative development within Timeboxes.
  • Timebox Level: Detailed planning for each individual Timebox, breaking down features into specific tasks for the team.
  • Daily Level: Individual team members plan their daily activities, often discussed during Daily Stand-ups.

## Monitoring and Control Mechanisms

Control in AgilePM is continuous, collaborative, and adaptive:

  • Daily Stand-ups: Essential for real-time progress monitoring, identifying and resolving issues, and fostering team collaboration.
  • Timebox Reviews: Provide regular opportunities for stakeholders to inspect the delivered increments and provide feedback, ensuring alignment with business needs.
  • Risk Management: Risks are continuously identified, assessed, and managed throughout the project lifecycle, with responses planned proactively.
  • Configuration Management: Ensures that all project products (e.g., code, documentation, test scripts) are version-controlled and managed effectively.
  • Estimation: Often uses relative estimation (e.g., Story Points) rather than absolute time, and velocity (the team's historical average work completion rate) to forecast future delivery. The Project Manager and Team Leader facilitate these processes, empowering the team to self-organise while maintaining project alignment.
  • AgilePM projects operate on a fixed time, fixed cost, variable scope model.
  • Timeboxing is the primary mechanism for planning and controlling work in AgilePM.
  • MoSCoW prioritisation (Must, Should, Could, Won't Have) manages scope within a Timebox.
  • Daily Stand-ups are crucial for daily progress monitoring, problem identification, and re-planning.
  • Planning occurs at Project, Phase, Timebox, and Daily levels.
  • Timebox Reviews involve demonstrating working solutions to stakeholders and gathering feedback.
  • Relative estimation and velocity are commonly used for forecasting in AgilePM.
  • Control in AgilePM is continuous, collaborative, and adaptive, not just at phase gates.
What is the primary planning and control mechanism in AgilePM?
Timeboxing.
tap to reveal
What is the AgilePM approach to time, cost, and scope?
Fixed time, fixed cost, variable scope.
tap to reveal
What does MoSCoW stand for in prioritisation?
Must Have, Should Have, Could Have, Won't Have (this time).
tap to reveal
What is the main purpose of a Daily Stand-up?
To monitor progress, identify impediments, and re-plan for the day.
tap to reveal
Name two levels of planning in AgilePM.
Project Level, Phase Level, Timebox Level, or Daily Level.
tap to reveal
What happens during a Timebox Review?
The team demonstrates working solutions to stakeholders and gathers feedback.
tap to reveal
How is scope managed within a fixed-duration Timebox?
Through MoSCoW prioritisation, ensuring Must Haves are delivered first.
tap to reveal
What is 'velocity' used for in AgilePM planning?
To forecast future delivery based on historical team performance.
tap to reveal

Key DSDM Practices

## Key DSDM Practices

AgilePM, built on the DSDM (Dynamic Systems Development Method) framework, employs several key practices to ensure successful, iterative delivery of business value. These practices promote collaboration, continuous improvement, and effective management of scope and time, forming the backbone of an AgilePM project.

Iterative Development

This core practice involves breaking down the project into smaller, manageable increments or iterations. Each iteration delivers a working, tested piece of the solution, allowing for early feedback and continuous refinement. This approach reduces risk, enables flexibility, and ensures the solution evolves to meet changing business needs effectively.

Timeboxing

Timeboxing is fundamental to DSDM. It involves fixing a period of time (a "timebox") for a specific activity or set of activities, with the objective of delivering the best possible solution within that timeframe. Resources and deadlines are fixed, while scope is variable and prioritised. This practice drives focus, prevents projects from overrunning, and ensures that something usable is always delivered by the deadline.

MoSCoW Prioritisation

This technique is used to prioritise requirements and deliverables effectively, ensuring that the most important items are delivered first. It categorises items into:

  • Must Have: Non-negotiable requirements essential for the solution to be viable.
  • Should Have: Important requirements that add significant value but are not critical for immediate delivery.
  • Could Have: Desirable requirements that would improve the solution but are less important.
  • Won't Have (for now): Requirements agreed not to be delivered in the current increment, to be revisited later.

MoSCoW ensures focus on critical items and manages expectations regarding scope.

Facilitated Workshops

These are structured, collaborative sessions involving key stakeholders and team members. They are highly effective for rapid information gathering, decision-making, and conflict resolution. Workshops promote shared understanding, build consensus, and accelerate progress compared to traditional serial meetings.

Modelling and Prototyping

Modelling involves creating visual representations (diagrams, flowcharts) of processes, data, or system components to aid understanding and communication among stakeholders. Prototyping involves building early, experimental versions of the solution to test ideas, gather user feedback, and validate requirements quickly. Both practices help to reduce ambiguity, confirm feasibility, and ensure the solution meets user needs before significant investment.

Daily Stand-ups and Retrospectives

Daily Stand-ups (or Daily Scrums) are short, timeboxed meetings where the team synchronises activities, shares progress, and identifies any impediments. They foster transparency and collaboration. Retrospectives are regular team meetings held at the end of an iteration or phase to review how the process went, identify what worked well, what didn't, and agree on improvements for future iterations. These practices drive continuous improvement within the team and project.

  • **Iterative Development** delivers working solutions in small, continuous increments for early feedback.
  • **Timeboxing** fixes the deadline and resources, allowing scope to be prioritised and flexed.
  • **MoSCoW Prioritisation** categorises requirements into Must, Should, Could, and Won't Have (for now).
  • **Facilitated Workshops** accelerate decision-making and build shared understanding among stakeholders.
  • **Modelling** creates visual representations; **Prototyping** builds early versions for feedback.
  • **Daily Stand-ups** are short, regular meetings to synchronise team progress and identify impediments.
  • **Retrospectives** are used to review processes and identify improvements for future iterations.
  • These DSDM practices are core to the AgilePM approach for effective project delivery.
What is the primary purpose of **Iterative Development** in DSDM?
To deliver working solutions in small, continuous increments, allowing for early feedback and refinement.
tap to reveal
How does **Timeboxing** manage project scope and deadlines?
It fixes the time and resources, allowing the scope (based on MoSCoW prioritisation) to be the variable, ensuring something usable is delivered by the deadline.
tap to reveal
List the four categories of **MoSCoW Prioritisation**.
Must Have, Should Have, Could Have, Won't Have (for now).
tap to reveal
What is the main benefit of using **Facilitated Workshops**?
They enable rapid information gathering, decision-making, and conflict resolution by bringing key stakeholders together collaboratively.
tap to reveal
Distinguish between **Modelling** and **Prototyping** as DSDM practices.
**Modelling** creates visual representations to aid understanding, while **Prototyping** builds early, experimental versions of the solution to test ideas and gather feedback.
tap to reveal
What is the purpose of a **Daily Stand-up** (or Daily Scrum)?
To synchronise team activities, share progress, and identify any impediments or blockers in a short, regular meeting.
tap to reveal
When are **Retrospectives** typically held and what is their aim?
Held at the end of an iteration or phase, their aim is to review the process, identify what worked and what didn't, and agree on improvements.
tap to reveal
Which DSDM practice ensures that essential requirements are always delivered within a timebox?
**MoSCoW Prioritisation**, specifically focusing on the "Must Have" requirements.
tap to reveal